Title:Expansion of Talimarjan Thermal Power Plant with the Construction of two Combined-Cycle Plants
Budget:7,145,033 EUR
Country:Uzbekistan
Dates: April, 2013 - September, 2017
Partner: Mott MacDonald Limited (UK)
Funding:ADB

The Government of Uzbekistan, together with the ADB, have embarked on implementing an important project to build Central Asia's first 800-900 megawatt CCGT power plant. This will expand the capacity of the Talimarjan Thermal Power Plant and improve management and operational capacity of the power utility.
Corporate Solutions was recruited to assist Uzbekenergo in assuring that the project is constructed to the specified standard in the bidding documents on the EPC contract, completed on schedule and with costs monitored and controlled. The consultant's role covers design audit and construction supervision of the contractors' works, issue of necessary progress reports, payment certificates and general project management.